Project deliverables
Project deliverables
The nine project deliverables for QUEST are summarised in the table below. These are published in section 9 of the full submission proforma.
As these deliverables are completed, the associated learning will be submitted to Ofgem and published below on the dates specified.
|
No. |
Deliverable | Deadline | Evidence | Status / Revised Date | |
|
1 |
QUEST Initial Report - Use Cases |
31/07/21 |
Document introducing the Project and detailing the use cases and scenarios. |
Completed July 21 |
|
|
2 |
QUEST System Design and Architecture Lessons Learned |
31/12/21 |
|
Completed December 21 |
|
|
3 |
QUEST Trials, Design and Specification Report |
30/06/22 |
Document explaining Project progress including the following outputs:
|
Completed June 22 |
|
|
4 |
QUEST Interim Report - System Design and Technology Build Lessons Learned |
30/06/23 |
Document detailing Porject progress to date including lessons learned from:
|
Completed June 23 |
|
|
5 |
QUEST System Integration Lessons Learned Report |
30/12/23 Revised Update: 30/04/24 Revised Additional IT update to be added |
Document detailing the lessons learned from the installation and commissioning of the QUEST system including system integration and the results of site acceptance testing. |
Completed December 23 Updated April 24 Last IT update December 24 |
|
|
6 |
Customer Research Findings Report |
31/10/24 Revised: 26/09/25 |
Document detailing the outputs from the customer research. |
Completed September 25 |
|
|
7 |
QUEST Trials and Analysis Report |
30/12/24 Revised: 28/11/25 |
Document detailing:
|
Completed November 25 |
|
|
8 |
QUEST Final Report |
30/04/25 Revised: 19/12/25 |
Report on the conclusion of the QUEST Project including all the lessons learned and detailing the next steps, including BaU transition. |
Completed December 25 |
|
|
9 |
Comply with knowledge transfer requirements of the Governance Document |
End of Project |
|
End of project |
Initial report - use cases
First deliverable report
System Design and Architecture Lessons Learned
Second deliverable report
Trials, Design and Specification Report
Third deliverable report
System Design and Technology Build Lessons Learned
Fourth deliverable report
QUEST System Integration Lessons Learned Report
Fifth deliverable report
Customer Research Report
Sixth deliverable report
Trials and Analysis Report
Seventh deliverable report