Quotation Options & Minimum Information

Quotation Options and Minimum Information

We offer a range of quotation options to suit your needs, including budget estimates, feasibility studies, Gen+ quotations (for generation projects ≥1MW), Point of Connection (PoC) offers and Full Detailed Quotes. Please note, a fee may apply to some quote options, particularly where more detailed network studies are required.

Please find below a list of the available quotation options, along with explanations and the minimum information required for each.

If you are unsure which quotation option you need to apply for, please contact our pre-application customer support team by emailing preapplicationsupport@enwl.co.uk or calling 0800 988 1732.

Details of our charges associated with the provision of quotations and estimates can be found in Section 7 of our Common Connection Charging Methodology.

 

A Budget Estimate

A budget estimate will provide you with an initial approximate price for your new connection. This is faster than a full detailed quote however, it cannot be accepted. The turnaround time to receive a budget estimate is 10 working days for <1MVA and 20 working days for >1MVA from when we receive your application.

Minimum Requirements:

  • Your name, correspondence address and contact details and preferred method of contact.
  • Site address and postcode including X & Y coordinates or What3Words.
  • Site location plan at an appropriate scale to indicate the site boundary.
  • The required Maximum Import Capacity (MIC) and Maximum Export Capacity (MEC) in kVA.
  • A summary of the technical details for any electricity generator that will be operating in parallel with the network.
  • A summary of the technical details for any equipment that could potentially affect the electricity supply, such as large motors, welders, or similar machinery.
  • Indicative date when the Customer requires the connection(s) to be made.

 

A Full Detailed Quote

A Full Detailed Quote provides a comprehensive quotation for your new connection. This will cover all of the anticipated costs associated with your new connection, split into contestable and non-contestable elements. This offer can be accepted in full.

Full detailed quotes are open to acceptance for 180 days, subject to our terms and conditions. In some cases, a charge will apply for the provision of the quotation offer, regardless of  whether you choose to accept it.

Please note that Generation Applications of 1MW and above, and Demand Applications of 5MVA and above, you must also provide the minimum information requirements outlined in the relevant section below.

Minimum Requirements:

  • Your name, correspondence address and contact details and preferred method of contact.
  • Site address and postcode including X & Y coordinates or What3Words.
  • Site Plan(s) (at an appropriate scale) detailing: 
    • The site location to include site boundary (typically outlined with a red line), with reference to adjacent footpaths and highways.
    • The site layout to include all buildings and access roads.
    • The proposed electricity meter point location (marked with an X).
    • The proposed substation location (for load over 300 kVA).
  • The required Maximum Import Capacity (MIC) and Maximum Export Capacity (MEC) in kVA, including a load breakdown where possible.
  • Preferred date for connection
  • The technical details of any electricity generator or storage device that will operate in parallel with the network, as set out in the relevant ENA Engineering Recommendation G98 or G99 Standard Application Forms
  • The technical details of any equipment that is likely to cause disturbance to the electricity supply, such as large motors, welders, or similar machinery.
  • Letter of authority where you are acting as an agent to the customer.

If you are installing generation equipment to a new or existing connection, we will also need the following information:

  • A completed  relevant ENA application form (G98/ G99)
  • Single Line Diagram (SLD)
  • Technical specifications for both new and existing generation, including inverter make and model or ENA reference (where available).
  • Existing Meter Point Administration Numbers (MPANs) (If you have an existing supply).

 

Point of Connection (PoC)

A Point Of Connection (PoC) offer identifies a suitable point of connection to our existing network for your required site load. This offer will also include any non-contestable works associated with your POC.

If you intend to appoint an Independent Connection Provider (ICP) to carry out the contestable works on your behalf, the ICP may submit this application for you.

PoC offers are open to acceptance for 180 days, subject to our terms and conditions. Please note that, in some cases, a charge will apply for the provision of the Point of Connection offer, regardless of  whether you choose to accept it.

Please note that Generation Applications of 1MW and above, and Demand Applications of 5MVA and above, you must also provide the minimum requirements outlined in the relevant section below.

Minimum Requirements:

  • Your name, correspondence address and contact details and preferred method of contact.
  • Site address and postcode including X & Y coordinates or What3Words.
  • Site Plan(s) (at an appropriate scale) detailing: 
    • The site location to include site boundary (typically outlined with a red line), with reference to adjacent footpaths and highways.
    • The site layout to include all buildings and access roads (for sites tp be adopted by the DNO).
    • The proposed electricity meter point location (marked with an X).
    • The proposed substation location (for load over 300 kVA).
  • The required Maximum Import Capacity (MIC) and Maximum Export Capacity (MEC) in kVA, including a load breakdown where possible.
  • Specify whether the network will be adopted by Distribution Network Operator (DNO) or an Independent Distribution Network Operator (IDNO).
  • The technical details of any electricity generator or storage device that will operate in parallel with the network, as set out in the relevant ENA Engineering Recommendation G98 or G99 Standard Application Forms.
  • The technical details for any customer-owned equipment that is likely to cause disturbance to the electricity supply, such as large motors, welders, or similar machinery.
  • Preferred date for connection

 

Generation Connection of  1MW and above:

For Generation applications of 1MW and above, we require the following information to be provided in addition to the minimum requirements detailed above, in order to provide a quotation. The new minimum information requirements apply to both Point of Connection (PoC) and full Connection Offers.

  • A letter of authority (LoA)
  • Heads of Terms (HoT) with a site layout plan clearly identifying all land relevant to the application (outlined in red as referred to in the HoT).
  • A detailed engineering design plan for the entire site, clearly showing the site boundary (outlined in red) and the location of key infrastructure and connection points.
  • Single line diagram of any on-site existing or proposed electrical plant.
  • A preliminary project timeline.
  • Mandatory completion of G99 SAF Part 4

Please refer to the ENA Guidance Document ‘DNO Queue Entry Requirements for Generation Schemes’ for more information.

 

Demand Connections of 5MVA and above:

For Demand applications of 5MVA and above submitted on or after 1st June 2026, we require the following information to be provided in addition to the minimum requirements detailed above, in order to provide a quotation. The new minimum information requirements apply to both Point of Connection (PoC) and full detailed quote offers.

  • Letter of Authority: a document signed by the Customer or Landowner where the Applicant is acting as an agent on their behalf.
  • Heads of Terms: where the Applicant or Customer is not the existing owner/leaseholder of the site, an appropriately signed agreement of Heads of Terms for the land indicated on the site plan (red line boundary).
  • Single Line Diagram: of any existing and/or proposed electrical plant (only required where there is customer owned equipment likely to cause disturbance).
  • Preliminary Project Timeline: to illustrate how the Applicant will meet the requested Connection Date.

Please refer to the ENA Guidance Document 'New Minimum Information Requirements for Distribution Demand Connections (>=5MVA) for more information.

 

A Feasibility Study

A feasibility study involves a more detailed assessment to consider a number options for connection and provide estimated costs for each option. This is not a connection offer and you will not be able to accept this quotation. There is a charge associated for this therefore we recommend you contact us first to find out more.

Minimum Requirements:

  • Your name, correspondence address and contact details and preferred method of contact.
  • Site address and postcode including X & Y coordinates or What3Words.
  • Site Plan(s) (at an appropriate scale) detailing: 
    • The site location to include site boundary (typically outlined with a red line), with reference to adjacent footpaths and highways.
    • The site layout to include all buildings and access roads.
    • The proposed electricity meter point location (marked with an X).
    • The proposed substation location (for load over 300 kVA).
  • A summary of the technical details for any electricity generator that will be operating in parallel with the network.
  • A summary of the technical details for any customer-owned equipment that could potentially affect the electricity supply, such as large motors, welders, or similar machinery.
  • Description of the range of options to be covered in the feasibility study.

 

Gen+

Applicable to generation projects of 1MVA or above, we will provide an budget estimate for up to six potential connection options at the same location. You have the opportunity to proceed to a formal connection offer/full detailed quote. If you confirm within seven working days, we will honour your original application received date for time to quote and to determine your position in the interactivity queue (if appropriate).

 There is a charge for this service, which is in addition to any further quotation costs, please refer to Quote costs (Connection Offer Expenses).

Minimum Requirements:

  • Your name, correspondence address and contact details and preferred method of contact.
  • Site address and postcode including X & Y coordinates or What3Words.
  • Site Plan(s) (at an appropriate scale) detailing: 
    • The site location to include site boundary (typically outlined with a red line), with reference to adjacent footpaths and highways.
    • The site layout to include all buildings and access roads.
    • The proposed electricity meter point location (marked with an X).
    • The proposed substation location (for load over 300 kVA).
  • The technical details of any electricity generator or storage device that will operate in parallel with the network, as set out in the relevant ENA Engineering Recommendation G98 or G99 Standard Application Forms.
  • The technical details for any customer-owned equipment that is likely to cause disturbance to the electricity supply, such as large motors, welders, or similar machinery.
  • Preferred date for connection
  • Letter of authority where are acting as an agent to the customer.

Quote costs (Connection Offer Expenses)

Distribution Network Operators (DNOs) are legally obliged to provide customers with an offer to connect to the electricity distribution network. From 6th April 2018, The Department for Business, Energy & Industrial Strategy (BEIS) introduced new regulations that allows DNOs to charge customers for their connection offer whether it is accepted or not.